Finishing Process - Alignment

C2020-02

1

The installation take place between the spaces of the metal gypsum board by using threaded rods, according specification.

2

The whole system is aligned with a suture or Laser.

3

Minor corrections at the bottom part of the system for a perfect elegant finishing. At the connection points a slightly sanding it may need by using a sandpaper.

4

The finishing process follows.

c2020

PVC TO PLASTERBOARD JOINT PROCEDURE

Our main goal is to provide products with competitive prices, short delivery time and excellent services. Having established ourselves in the construction of the island. C2020 by Ventus Air Technologies and D. Ellinas Factory Products aspires to grow even more each year by being another creative “tool” for the lovers of modern design and innovative products.

Step 1

Use double threaded screws to fasten PVC grille in place and secure a tight fit along with the plasterboard.

Step 2

Slightly scrab the PVC surface to make it rougher using sandpaper. Fill the small gap between PVC surface and gypsumboard by applying a thin and even layer of the special joint filler compound.

Step 3

Instantly after step 2 and when compound is still wet, place and stick a special textile fiber glass joint tape on it and let it dry.

Step 4

Apply a thin and even layer of the special joint filler compound on top of fiber glass joint tape and let it dry.

Step 5

Using a fine grid sandpaper scrab the surface till Becomes smooth. Then is ready to be painted.

Finishing Process C2020 - Alignment